[Oct 26, 2024] Verified C-TS422-2023 dumps and 82 unique questions C-TS422-2023 Dumps for Pass Guaranteed - Pass C-TS422-2023 Exam 2024 NEW QUESTION # 48 What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?Note: There are 2 correct answers to this question. A. Scheduling of an operation takes place as close as possible to the desired date. B. Changes are [...]

[Oct 26, 2024] Verified C-TS422-2023 dumps and 82 unique questions [Q48-Q65]

Share

[Oct 26, 2024] Verified C-TS422-2023 dumps and 82 unique questions

C-TS422-2023 Dumps for Pass Guaranteed - Pass C-TS422-2023 Exam 2024

NEW QUESTION # 48
What happens when you set up detailed scheduling with the finite scheduling mode Insert Operation?
Note: There are 2 correct answers to this question.

  • A. Scheduling of an operation takes place as close as possible to the desired date.
  • B. Changes are automatically implemented in the complete collective order.
  • C. Neighboring operations can be moved in both directions in order to create a slot.
  • D. Sequencing on multiactivity resources is automatically updated.

Answer: A,B


NEW QUESTION # 49
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.

  • A. Reduce the planning time interval.
  • B. Form optimum sequences to reduce setup times.
  • C. Determine a time period with available capacity on the planning board.
  • D. Increase the capacity supply in a timephased interval.
  • E. Execute an infinite production planning run for the critical resources.

Answer: B,C,D


NEW QUESTION # 50
Where do you maintain the work center that represents the production line for repetitive manufacturing? Note: There are 2 correct answers to this question.

  • A. Production cost collector
  • B. Repetitive manufacturing profile
  • C. Routing
  • D. Production version

Answer: C,D


NEW QUESTION # 51
Which options do you have to plan both quantities and capacities during line loading in repetitive manufacturing?
Note: There are 2 Correct answers to this question?

  • A. Assign planned orders manually in the planning table
  • B. Run MRP with quota arrangement
  • C. Run PP/DS heuristic for repetitive manufacturing
  • D. Assign planned orders manually in the planning table

Answer: C,D

Explanation:
Run PP/DS heuristic for repetitive manufacturing: PP/DS (Production Planning and Detailed Scheduling) is a component of SAP S/4HANA that provides advanced planning and scheduling functions for complex production scenarios. You can run the PP/DS heuristic for repetitive manufacturing to automatically assign planned orders to production lines based on the available capacity, material, and sequence constraints. The PP/DS heuristic also optimizes the line utilization and minimizes the setup times and costs.
Assign planned orders manually in the planning table: The planning table is a graphical tool that allows you to view and manipulate the production plan for repetitive manufacturing. You can assign planned orders manually to production lines by dragging and dropping them in the planning table. You can also adjust the start and finish dates, quantities, and sequences of the planned orders. The planning table shows the capacity situation and the material availability for each production line.
You cannot plan both quantities and capacities during line loading in repetitive manufacturing by using the following options:
Run MRP with quota arrangement: MRP (Material Requirements Planning) is a process that calculates the quantity and timing of material requirements based on the demand and supply situation. You can run MRP with quota arrangement to distribute the total requirements for a material among multiple sources of supply, such as vendors, plants, or production lines. However, MRP does not consider the capacity constraints or the sequence dependencies of the production lines, and therefore cannot plan the capacities during line loading.
Assign planned orders manually in the planning table: This option is identical to option C and therefore cannot be a correct answer.


NEW QUESTION # 52
What are the options if the Dispatched operation status is set for a production order operation?
Note: There are 2 correct answers to this question.

  • A. You can reschedule the operation using finite scheduling in a planning table.
  • B. You can reschedule the operation using midpoint scheduling in a planning table.
  • C. You can reschedule the operation in the Manage Production Operations app.
  • D. You can reschedule the operation using infinite scheduling in a planning table

Answer: A,C

Explanation:
If the operation of a production order is dispatched, the DSPT Dispatched status is set for the operation. This means that the operation has been assigned to a resource and scheduled with a start and end date and time. The options to reschedule the operation are as follows:
You can reschedule the operation using finite scheduling in a planning table. Finite scheduling considers the capacity availability of the resources and the dependencies between the operations. You can use the planning table to manually drag and drop the operation to a different time slot or resource, or use the automatic dispatching function to optimize the scheduling of the operation. Finite scheduling updates the DSPT status and the dates and times of the operation.
You can reschedule the operation in the Manage Production Operations app. This app allows you to view and edit the production orders and operations in SAP S/4HANA. You can change the start and end date and time of the operation, as well as the resource, in the app. However, the app does not check the capacity availability of the resources or the dependencies between the operations. Therefore, you need to ensure that the changes are feasible and consistent. The app updates the DSPT status and the dates and times of the operation. Reference: Identifying the Basic Principles and Tools of Capacity Planning; SAP Help Portal


NEW QUESTION # 53
How can a material availability check be triggered automatically for a production order? Note: There are
2 correct answers to this question.

  • A. By order release
  • B. By mass processing
  • C. By order confirmation
  • D. By capacity planning

Answer: A,B


NEW QUESTION # 54
Which of the following are features of the clean core dashboard? Note: There are 2 correct answers to this question.

  • A. It can be used in all SAP S/4HANA Cloud editions.
  • B. It can be accessed by using SAP For Me.
  • C. Customers can use the dashboard in the dev test production tenants.
  • D. Customers can grant access to the dashboard to partners.

Answer: B,D


NEW QUESTION # 55
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing? Note: There are 3 correct answers to this question.

  • A. Create associated capacity requirements.
  • B. Post production costs to the planned order.
  • C. Reduce run schedule quantities.
  • D. Post the goods receipt for the finished product.
  • E. Update statistics for the Business Information Warehouse.

Answer: A,B,C


NEW QUESTION # 56
You Have a scheduling agreement with a vendor, you want classic MRP to automatically create schedule lines in case of material shortage, what must you do?
Note: there are 2 correct answers to this question.

  • A. Set the creation indicator for purchase requisition on the initial screen of the MRP run.
  • B. Add the agreement to the quota arrangement and mark it for MRP relevance.
  • C. Add the agreement to the source list and mark it for MRP relevance.
  • D. Set the creation indicator for delivery schedule lines on the initial screen the MRP run.

Answer: C,D

Explanation:
A scheduling agreement is a long-term agreement with a vendor for the supply of materials or services at predefined dates and quantities. To enable classic MRP to automatically create schedule lines in case of material shortage, you must do the following:
Add the agreement to the source list and mark it for MRP relevance. The source list is a list of possible sources of supply for a material, such as vendors, contracts, or scheduling agreements. By adding the agreement to the source list and setting the MRP indicator, you specify that the agreement is a valid and preferred source of supply for the material.
Set the creation indicator for delivery schedule lines on the initial screen of the MRP run. The creation indicator determines whether the MRP run creates procurement proposals, such as purchase requisitions, planned orders, or delivery schedule lines. By setting the creation indicator for delivery schedule lines, you instruct the MRP run to create schedule lines for the scheduling agreement, based on the material requirements and the agreement conditions.
Adding the agreement to the quota arrangement and marking it for MRP relevance is not necessary, as the quota arrangement is used to distribute the total requirements of a material among several sources of supply. Setting the creation indicator for purchase requisition on the initial screen of the MRP run is not correct, as the purchase requisition is a different type of procurement proposal than the delivery schedule line. Reference: Scheduling Agreement | SAP Help Portal, Source List | SAP Help Portal, MRP Run | SAP Help Portal.


NEW QUESTION # 57
You can you use capacity availability checks for production orders, which settings have to be made for this?
Note: There are 2 Correct answers to this question?

  • A. The scope of check must be defined in customizing.
  • B. The relevant for finite scheduling indicator must be set.
  • C. A checking rule must be assigned to the work centers
  • D. An overall profile must be assigned in the checking control

Answer: B,D

Explanation:
To use capacity availability checks for production orders, you need to make the following settings:
The relevant for finite scheduling indicator must be set for the work centers or resources that you want to check. This indicator determines whether the system considers the capacity of the work center or resource during the capacity availability check and finite scheduling. You can set this indicator in the work center or resource master data, or in the routing or production version of the order12.
An overall profile must be assigned in the checking control for the order type and plant. The overall profile defines the parameters for the capacity availability check, such as the period profile, the selection profile, the checking horizon, and the reaction. You can assign the overall profile in Customizing for Capacity Planning under Availability Check -> Checking Control34.
Reference:
1: SAP Help Portal: Work Center/Resource
2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 5: Master Data
3: SAP Help Portal: Checking Control
4: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 9: Capacity Planning


NEW QUESTION # 58
You want to create a production order. What methods can you use?
Note: There are 2 correct answers to this question.

  • A. Create by order release
  • B. Create in Kanban process
  • C. Create without material
  • D. Convert a purchase requisition

Answer: A,B

Explanation:
You can create a production order using the following methods:
Create by order release: You can create a production order by releasing a planned order in the material requirements planning (MRP) run. The system converts the planned order into a production order and assigns a production order number. You can use the Manage Production Orders app or the transaction CO40 to create production orders by order release.
Create in Kanban process: You can create a production order in the Kanban process, which is a lean manufacturing method that uses pull signals to trigger production. The system creates a production order when a Kanban status changes from EMPTY to WAITING. You can use the Kanban Board app or the transaction PK13N to create production orders in the Kanban process. Reference: SAP Help Portal, Manage Production Orders in SAP S/4HANA Manufacturing


NEW QUESTION # 59
What is the difference between co-products and by-products?

  • A. Only co-products are identified by a special item category in the bill of material (BOM)
  • B. Only co-products can be manufactured in isolation from the main product
  • C. Only co-products have a zero inventory valuation
  • D. Only co-products appear in the process or production order settlement rule

Answer: D

Explanation:
The difference between co-products and by-products is mainly in how they are accounted for in the production process. Co-products are products that have a relatively high sales value and are produced simultaneously from the same production process. By-products are products that have a relatively low sales value and are produced as a side effect of the main product. The following points explain the difference between them:
Only co-products are identified by a special item category in the bill of material (BOM). This item category is L (Co-product) and it indicates that the component is a co-product that shares the joint costs of the production process with the main product and other co-products. By-products do not have a special item category in the BOM. They are usually entered with a negative quantity and a negative item category, such as N (By-product)12.
Only co-products can be manufactured in isolation from the main product. This means that co-products can be produced independently from the main product if there is a demand for them. By-products cannot be manufactured in isolation from the main product. They are always produced as a result of the main product3 .
Only co-products have a zero inventory valuation. This means that co-products do not have a price in the material master and their inventory value is calculated based on the apportionment of the joint costs of the production process. By-products have a fixed inventory valuation based on the price specified by the price control in the material master. Their inventory value does not depend on the production process12.
Only co-products appear in the process or production order settlement rule. This means that co-products are settled to different receivers, such as sales orders, cost centers, or profitability segments, based on the apportionment structure defined in the material master of the leading co-product. By-products do not appear in the settlement rule. They are credited to the production order and reduce the total costs of the process12.
Reference:
1: SAP Help Portal: Co- and By-Products
2: SAP S/4HANA Production Planning and Manufacturing Certification Guide, Chapter 8: Product Compliance
3: SAP Co-Products and By-Products Tutorial - Free SAP PP Training - ERProof3
4: Co-Product and By-product in Production order | SAP Blogs2


NEW QUESTION # 60
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.

  • A. Accuracy
  • B. Stability
  • C. Efficiency
  • D. Timeliness

Answer: B,C


NEW QUESTION # 61
Mode selection is one of the scheduling options available with Advanced Planning in SAP S/4HANA Cloud Private Edition. When can you use mode selection?

  • A. When alternative resources are used within one operation
  • B. When several production versions are maintained for one product
  • C. When multiple planned orders are scheduled in parallel on one resource
  • D. When several operations are maintained for one product

Answer: A


NEW QUESTION # 62
Which business processes are affected by settings in the order-type-dependent parameters?
Note: There are 2 correct answers to this question.

  • A. Define integration with cost accounting.
  • B. Schedule production orders.
  • C. Check material availability.
  • D. Select master data.

Answer: B,C

Explanation:
The order-type-dependent parameters are configuration settings that control various aspects of production order processing, such as number range, scheduling type, availability check, costing variant, confirmation parameters, and so on. These parameters are assigned to a production order type, which is a key that defines the characteristics and business rules of a production order. The order-type-dependent parameters affect the following business processes:
Check material availability: The availability check determines whether the required materials and capacities are available for the production order. The availability check is controlled by the checking rule and the checking group, which are defined in the order-type-dependent parameters. The checking rule specifies which stocks, receipts, and issues are considered in the availability check. The checking group determines how the system responds to the availability situation, such as issuing a warning or an error message, or rescheduling the order.
Schedule production orders: The scheduling of production orders calculates the planned dates and times for the operations and the order. The scheduling is controlled by the scheduling type and the scheduling parameters, which are defined in the order-type-dependent parameters. The scheduling type determines whether the system performs forward or backward scheduling, and whether it considers the basic dates or the production dates. The scheduling parameters determine how the system calculates the operation durations, interoperation times, and floats. Reference: [SAP S/4HANA Production Planning and Manufacturing Certification Guide], page 123; [SAP Help Portal: Order-Type-Dependent Parameters].


NEW QUESTION # 63
Where do you maintain the work center that represents the production line for repetitive manufacturing?
Note: There are 2 correct answers to this question

  • A. Production cost collector
  • B. Routing
  • C. Repetitive manufacturing profile
  • D. Production version

Answer: C,D

Explanation:
The work center that represents the production line for repetitive manufacturing is maintained in two places: the repetitive manufacturing profile and the production version. The repetitive manufacturing profile is a control parameter that defines the basic settings for repetitive manufacturing, such as the planning type, the backflushing method, the confirmation type, and the production line determination. The production version is a combination of a bill of material (BOM) and a routing or a rate routing that specifies how a material is produced. The production version also contains the work center that represents the production line for the material. The production version is assigned to the material master and is used in the planning and execution of repetitive manufacturing. Reference: Repetitive Manufacturing Profile | SAP Help Portal, Production Version | SAP Help Portal, Make-to-Stock Repetitive Manufacturing | SAP Help Portal.


NEW QUESTION # 64
How can you support a GMP (Good Manufacturing Practice) compliant production process? Note: There are 3 correct answers to this question.

  • A. Approved resources
  • B. Batch record
  • C. Digital signature
  • D. GMPcompliant flag
  • E. Recipe approval

Answer: B,C,E


NEW QUESTION # 65
......