
New 2024 CPIM-8.0 exam questions Welcome to download the newest RealValidExam CPIM-8.0 PDF dumps (152 Q&As)
P.S. Free 2024 Certified Production and Inventory Management CPIM-8.0 dumps are available on Google Drive shared by RealValidExam
NEW QUESTION # 25
In a make-to-stock (MTS) environment, the master production schedule (MPS) Is usually a schedule of which of the following types of items?
- A. Finished goods items
- B. Phantom items
- C. Raw material items
- D. Component/subassembly items
Answer: A
Explanation:
In a make-to-stock (MTS) environment, the master production schedule (MPS) is usually a schedule of finished goods items that are ready to be sold to customers. Phantom items, component/subassembly items, and raw material items are not typically scheduled in the MPS, but rather in the material requirements planning (MRP) system, which is driven by the MPS. References:
CPIM 8.0 Exam Content Manual Preview, page 10, section 4.1.1
CPIM Part 1 Study Guide, page 66, section 4.1.1
CPIM Part 1 Learning System, Module 4, Lesson 1, Topic 1: Master Production Schedule
NEW QUESTION # 26
Capacity requirements planning (CRP) is applicable primarily In companies operating In an environment where:
- A. backlog is very low.
- B. lean principles are used.
- C. material requirements planning (MRP) is used.
- D. the status of work orders is disregarded.
Answer: C
Explanation:
Capacity requirements planning (CRP) is a technique that calculates the capacity needed to produce the planned orders generated by material requirements planning (MRP). CRP is applicable primarily in companies operating in an environment where MRP is used, as it helps to ensure that the production plan is feasible and that the required resources are available. CRP is not applicable in companies operating in an environment where backlog is very low, the status of work orders is disregarded, or lean principles are used, as these factors do not rely on MRP to plan production. References: Capacity Requirements Planning | APICS Dictionary Term of the Day, APICS CPIM 8 Planning and Inventory Management | ASCM
NEW QUESTION # 27
Which of the following trade-offs should be evaluated when determining where to place inventory in a multi-echelon supply chain network?
- A. Production cost and lot size quantity
- B. Purchase cost and shrinkage rates
- C. Customer price and order quantity
- D. Transportation cost and delivery time
Answer: D
Explanation:
Transportation cost and delivery time are two of the trade-offs that should be evaluated when determining where to place inventory in a multi-echelon supply chain network. A multi-echelon supply chain network consists of multiple levels of distribution, such as factories, warehouses, distribution centers, and retailers.
Placing inventory closer to the customers can reduce the delivery time and improve the service level, but it can also increase the transportation cost and the inventory holding cost. Placing inventory farther from the customers can reduce the transportation cost and the inventory holding cost, but it can also increase the delivery time and the risk of stockouts. Therefore, the optimal inventory placement depends on balancing these trade-offs and finding the lowest total cost for the desired service level. The other trade-offs are not directly related to inventory placement in a multi-echelon supply chain network. Production cost and lot size quantity are more related to inventory replenishment policies and economies of scale. Purchase cost and shrinkage rates are more related to inventory sourcing and quality control. Customer price and order quantity are more related to demand management and pricing strategies. References: Network Design and Safety Stock Placement for a Multi-Echelon Supply Chain, APICS CPIM 8 Planning and Inventory Management | ASCM
NEW QUESTION # 28
In a rapidly changing business environment, a primary advantage of an effective customer relationship management (CRM) program is:
- A. fewer customer order changes.
- B. fewer customer defections.
- C. reduced forecast variability.
- D. earlier Identification of shifts Incustomer preferences.
Answer: D
Explanation:
In a rapidly changing business environment, a primary advantage of an effective customer relationship management (CRM) program is earlier identification of shifts in customer preferences. CRM is a strategy that focuses on building and maintaining long-term relationships with customers by understanding their needs, preferences, and behaviors. CRM enables organizations to anticipate and respond to changes in customer demand, improve customer satisfaction and loyalty, and increase profitability and competitiveness. CRM also helps organizations to segment and target customers based on their value and potential, and to customize products and services accordingly. CRM involves the use of various tools and techniques, such as data collection and analysis, communication channels, feedback mechanisms, and loyalty programs. References:
Managing Supply Chain Operations, Chapter 4: Customer Relationship Management, Section 4.1:
Introduction to Customer Relationship Management
CPIM Exam Content Manual, Module 1: Supply Chains and Strategy, Section 1.2: Customer Relationship Management, Subsection 1.2.1: Customer Relationship Management Concepts
NEW QUESTION # 29
Which of the following methods most likely Introduces a temporary variance between the inventory balance and the inventory record?
- A. Backflushing
- B. Inventory write-off
- C. Kanban
- D. Cycle count
Answer: A
Explanation:
Backflushing is a method of inventory accounting that deducts the materials used in production from the inventory record after the completion of a product or batch. This introduces a temporary variance between the actual inventory balance and the inventory record, which should be reconciled periodically. Inventory write-off, cycle count, and kanban do not cause such a variance. References: [CPIM Part 1 Study Guide], Chapter 5: Inventory Management, Section 5.3: Inventory Record Accuracy, p. 5-15.
NEW QUESTION # 30
In which of the following phases of the product life cycle is product price most effective in influencing demand?
- A. Maturity
- B. Decline
- C. Growth
- D. Introduction
Answer: D
Explanation:
Product price is most effective in influencing demand in the introduction phase of the product life cycle, when the product is new and unfamiliar to the market. In this phase, customers are not aware of the product's benefits, features, or quality, and may be reluctant to try it. Therefore, a lower price can help attract customers and stimulate demand, as well as deter potential competitors from entering the market. A lower price can also help the product gain market share and establish a loyal customer base. As the product moves to the growth, maturity, and decline phases, price becomes less effective in influencing demand, as other factors, such as product differentiation, quality, promotion, and customer satisfaction, become more important. References:
*Product Life Cycle Explained: Stage and Examples
*The 6 Stages of the Product Life Cycle [+Examples]
*Product Life Cycle - Definition, Stages, Usage
NEW QUESTION # 31
Which of the following statements characterizes a pull system In distribution management?
- A. It uses distribution requirements planning(DRP).
- B. Each warehouse makes its own replenishment decisions.
- C. It uses fair-share allocation.
- D. It uses uniform performance measures.
Answer: B
Explanation:
A pull system in distribution management is a method of inventory replenishment that is driven by the actual demand of the customers, rather than by forecasts or schedules. In a pull system, each warehouse makes its own replenishment decisions based on the inventory level and the customer orders. A pull system reduces the risk of overstocking or understocking inventory, as it responds to the real-time demand fluctuations. A pull system also improves the efficiency and flexibility of the distribution network, as it eliminates the need for centralized planning and coordination. A pull system is suitable for products that have high demand uncertainty, low holding costs, or short lead times12. References: Push vs. Pull Inventory Management Systems 2023 | Business.org, Push vs. pull: Inventory management for distribution businesses
NEW QUESTION # 32
During the sales and operations planning (S&OP) process, which of the following tasks is the primary responsibility of the functional representatives on the supply planning team?
- A. Understanding how to use the plan to improve functional performance
- B. Ensuring that the functional objectives are considered when developing the plans
- C. Identifying reasons why the demand plan is not realistic
- D. Communicating when an event will prevent meeting the supply plan
Answer: B
Explanation:
The supply planning team is responsible for developing a supply plan that balances the demand plan with the available resources and capacities. The functional representatives on the supply planning team, such as production, procurement, engineering, and finance, need to ensure that their functional objectives are considered when developing the plans. For example, production needs to consider the impact of the supply plan on the production schedule, capacity utilization, and labor requirements. Procurement needs to consider the impact of the supply plan on the supplier relationships, lead times, and inventory levels. Engineering needs to consider the impact of the supply plan on the product design, quality, and innovation. Finance needs to consider the impact of the supply plan on the costs, revenues, and profitability. By ensuring that the functional objectives are considered, the supply planning team can create a feasible and optimal supply plan that aligns with the overall business strategy12. References: 1 S&OP: A Comprehensive Overview of Sales and Operations Planning 3 2 CPIM Exam References - Association for Supply Chain Management 1
NEW QUESTION # 33
The question below is based on the following information:
Beginning inventory = 43Week 1Week 2Week 3
Forecast202020
Customer orders221710
Projected on-hand
Master production schedule (MPS)80
Available-to-promise (ATP)
What is the largest customer order that could be accepted for delivery at the end of week 3 without making changes to the master production schedule (MPS)?
- A. 0
- B. 1
- C. 2
- D. 3
Answer: B
Explanation:
Available-to-promise (ATP) is the uncommitted portion of a company's inventory and planned production maintained in the master schedule to support customer-order promising. ATP is calculated by subtracting the customer orders and forecast from the projected on-hand inventory. The projected on-hand inventory is calculated by adding the beginning inventory and the master production schedule (MPS) and subtracting the customer orders.The largest customer order that could be accepted for delivery at the end of week 3 without making changes to the MPS is the ATP at the end of week 3. To calculate the ATP, we need to fill in the projected on-hand inventory for each week using the given information:
Table
Week
Forecast
Customer Orders
MPS
Projected On-Hand Inventory
ATP
1
20
22
0
43 + 0 - 22 = 21
21 - 20 = 1
2
20
17
0
21 + 0 - 17 = 4
4 - 20 = -16
3
20
10
80
4 + 80 - 10 = 74
74 - 20 = 54
The ATP at the end of week 3 is 54, which means that the company can promise 54 units of inventory to customers without changing the MPS. However, the question asks for the largest customer order that could be accepted, which means that we need to consider the existing customer orders as well. The customer orders for week 3 are 10, which means that the company has already committed 10 units of inventory to customers.
Therefore, the largest customer order that could be accepted for delivery at the end of week 3 is 54 + 10 = 64 units. However, this is not one of the options given in the question. The closest option that is less than or equal to 64 is 61, which is option C12 References: 1: CPIM Part 1 - Section A - Module 1 - Session 4 - Master Scheduling 2: CPIM Part 1 - Section A - Module 1 - Session 5 - Available to Promise
NEW QUESTION # 34
In the design and development of a manufacturing process, process engineers would most likely be responsible for decisions relating to:
- A. production capacity.
- B. product reliability.
- C. routing sequences.
- D. lead times.
Answer: C
Explanation:
Process engineers are responsible for designing, implementing, controlling, and optimizing industrial processes, especially continuous ones such as the production of petrochemicals1. One of the decisions that process engineers would most likely make is the routing sequence, which is the order of operations or activities that are performed on a product or material as it moves through the production process2. The routing sequence affects the process performance, efficiency, quality, and cost, and it requires careful planning and analysis by the process engineers. Option A is not correct, because lead times are the time intervals between the initiation and completion of a process or a project3. Lead times are influenced by many factors, such as demand, capacity, inventory, scheduling, and supply chain management, and they are not solely determined by the process engineers. Option B is not correct, because production capacity is the maximum amount of output that a process or a system can produce within a given period of time4. Production capacity depends on the availability and utilization of resources, such as materials, labor, equipment, and facilities, and it is not only decided by the process engineers. Option C is not correct, because product reliability is the probability that a product will perform its intended function without failure for a specified period of time under specified conditions5. Product reliability is affected by many aspects, such as product design, quality control, testing, maintenance, and customer feedback, and it is not the sole responsibility of the process engineers. References:
1 Process engineering - Wikipedia 6 2 Routing (production) - Wikipedia 7 3 Lead Time: Definition, Formula, and Examples 8 4 Production Capacity: Definition, Calculation, and Examples 9 5 Product Reliability:
Definition, Measurement, and Improvement
NEW QUESTION # 35
A manufacturer has a primary assembly line supported by output from several subassembly lines. Which of the following scenarios would be the best argument for a multilevel master scheduling process?
- A. High variation in aggregate subassembly demand
- B. High variation in subassembly demand mix
- C. Low variation in subassembly demand mix
- D. Low variation in aggregate subassembly demand
Answer: B
Explanation:
A multilevel master scheduling process is a method of planning and managing the production of complex products that have multiple levels of components and subassemblies. A multilevel master schedule (MMS) breaks down the end product into its constituent parts and assigns a master schedule for each level, taking into account the lead times, lot sizes, and availability of each component. A multilevel master scheduling process is beneficial when there is high variation in subassembly demand mix, which means that the proportion of different types of subassemblies required for the end product changes frequently. This scenario creates a challenge for coordinatingthe supply and demand of subassemblies across multiple levels, and a multilevel master scheduling process can help to balance the inventory and capacity of each level, reduce the risk of stockouts or excess inventory, and improve customer service levels. References := CPIM Part 2 Exam Content Manual, Version 8.0, ASCM, 2021, p. 23. CPIM Part 2 Learning System, Version 8.0, Module 2, Section B,
NEW QUESTION # 36
A company assembles kits of hand tools after receipt of the order from distributors and uses two-level master scheduling. The appropriate levels of detail for the forecasts that are input to master scheduling would be total number of kits and:
- A. specific kit configurations.
- B. raw material requirements.
- C. each unique tool.
- D. percentage of total for each tool.
Answer: A
Explanation:
A company that uses two-level master scheduling has a master production schedule (MPS) for the end items (kits) and a final assembly schedule (FAS) for the components (tools). The forecasts that are input to master scheduling should reflect the total number of kits and the specific kit configurations, as these determine the demand for the components. The other options are not relevant for master scheduling, as they do not reflect the end item demand or the bill of materials structure. References: EXAM CONTENT MANUAL PREVIEW, page 10, section 4.1.2. Manufacturing Planning and Control for Supply Chain Management: The CPIM Reference, Second Edition, page 163, section 6.2.
NEW QUESTION # 37
Which of the following inventory management techniques is most responsive to changes in demand levels?
- A. ABC classification
- B. Two-bin system
- C. Cycle counting
- D. Periodic review system
Answer: D
Explanation:
A periodic review system is an inventory management technique where the inventory level is checked at fixed intervals and replenishment orders are placed according to the current demand and inventory position. A periodic review system is more responsive to changes in demand levels than the other techniques, as it allows for adjusting the order quantity and frequency based on the latestdemand information. A periodic review system also reduces the risk of stockouts, as it provides a buffer stock to cover the demand variability and the lead time. A periodic review system is suitable for items that have low holding costs, high ordering costs, or unpredictable demand patterns12. References: Periodic Review System - Inventory Management - MBA Knowledge Base, Inventory Management: How to Organize and Plan Effectively - G2
NEW QUESTION # 38
A manufacturer has a forecasted annual demand of 1,000,000 units for a new product. They have to choose 1 of 4 new pieces of equipment to produce this product. Assume that revenue will be $10 per unit for all 4 options.
Which machine will maximize their profit if the manufacturer anticipates market demand will be steady for 3 years and there is no residual value for any of the equipment choices?
MachineFixed CostVariable Cost per UnitAnnual Capacity
AS100.000$6 00800,000 units
B$200,000$5 501.000,000 units
C$250,000$5 001,200,000 units
D$1 000.000$4 501 400.000 units
- A. Machine B
- B. Machine C
- C. Machine A
- D. Machine D
Answer: B
Explanation:
To maximize profit, the manufacturer should choose the machine that has the lowest total cost per unit of demand. The total cost per unit of demand is calculated by adding the fixed cost per unit of demand and the variable cost per unit. The fixed cost per unit of demand is obtained by dividing the fixed cost by the annual demand. The variable cost per unit is given in the table. The total cost per unit of demand for each machine is:
Machine A: 1,000,000100,000+6.00=6.10
Machine B: 1,000,000200,000+5.50=5.70
Machine C: 1,000,000250,000+5.00=5.25
Machine D: 1,000,0001,000,000+4.50=5.50
The lowest total cost per unit of demand is for Machine C, which is $5.25. Therefore, Machine C will maximize the profit for the manufacturer.
References:
Some possible references for this question are:
CPIM Part 1 Exam Content Manual, Version 8.0, Domain 3: Plan and Manage Supply, Section A: Plan and Manage Supply Chain Capacity, Topic 2: Capacity Planning Concepts, Subtopic b: Capacity planning methods, Page 30 CPIM Part 1 Learning System, Version 8.0, Module 3: Plan and Manage Supply, Section 3.2: Capacity Planning Concepts, Topic 3.2.2: Capacity Planning Methods, Subtopic 3.2.2.2: Cost-Volume Analysis, Pages 3-24 to 3-26 CPIM Part 1 Study Guide, Version 8.0, Module 3: Plan and Manage Supply, Section 3.2: Capacity Planning Concepts, Topic 3.2.2: Capacity Planning Methods, Subtopic 3.2.2.2: Cost-Volume Analysis, Pages 3-24 to 3-26
NEW QUESTION # 39
The most relevant measure of customer service performance Is:
- A. customer complaints received as a percentage of orders shipped.
- B. service perceived by the customer against service expected by the customer.
- C. positive customer feedback as a percentage of customer feedback.
- D. service promised to the customer against service measured by the supplier.
Answer: B
Explanation:
Customer service performance is the degree to which a company meets or exceeds the expectations of its customers in terms of the quality, timeliness, and satisfaction of the service provided. The most relevant measure of customer service performance is the service perceived by the customer against the service expected by the customer, also known as the service quality gap. This measure captures the difference between what customers expect from a service and what they actually receive, and reflects the level of customer satisfaction or dissatisfaction. A positive service quality gap indicates that the service exceeded the expectations, while a negative service quality gap indicates that the service fell short of the expectations. The other options are not as relevant as the service quality gap because they do not account for the customer's perspective or perception of the service. Service promised to the customer against service measured by the supplier is an internal measure of service performance, but it does not reflect how the customer perceives the service. Customer complaints received as a percentage of orders shipped is a measure ofservice failure, but it does not capture the positive feedback or the silent dissatisfied customers. Positive customer feedback as a percentage of customer feedback is a measure of service satisfaction, but it does not account for the customer's expectations or the service quality dimensions. References:
CPIM Part 2 Exam Content Manual, p. 67
Customer Service Metrics: Top 10 to Measure
20 Customer Service KPIs You Need To Know
NEW QUESTION # 40
A company can easily change Its workforce, but inventory carrying costs are high. Which of the following strategies would be most appropriate during times of highly fluctuating demand?
- A. Produceto demand
- B. Produceto the sales forecast
- C. Produceto backorders
- D. Produceat a constant level
Answer: A
Explanation:
Producing to demand is a strategy that adjusts the production output to match the actual customer demand.
This strategy is most appropriate during times of highly fluctuating demand, as it can reduce the inventory carrying costs and avoid overproduction or underproduction. Producing to demand can also improve customer satisfaction and responsiveness, as well as reduce waste and obsolescence. However, producing to demand requires a flexible and adaptable workforce that can easily change its capacity and skills to meet the changing demand patterns. The other options, producing to backorders, producing at a constant level, and producing to the sales forecast, are not as effective as producing to demand during times of highly fluctuating demand, as they can result in higher inventory costs, lower customer service, and lower profitability. References:
Demand-Driven Manufacturing: What It Is and Why You Need It
Demand-Driven Manufacturing: How to Optimize Your Production Process
Demand-Driven Manufacturing: A Guide for Modern Manufacturers
NEW QUESTION # 41
A company confirms a customer order based on available capacity and inventory, even though the current production plan does not cover the entire order quantity. This situation is an example of what type of order fulfillment policy?
- A. Configure-to-order (CTO)
- B. Available-to-promise (ATP)
- C. Capable-to-promise (CTP)
- D. Assemble-to-order (ATO)
Answer: C
Explanation:
Capable-to-promise (CTP) is a type of order fulfillment policy that confirms a customer order based on the available capacity and inventory, as well as the current production plan and schedule. CTPcalculates the earliest possible delivery date for a customer order, considering the existing demand and supply situation. CTP allows a company to accept an order that exceeds the current available inventory, as long as it can produce the remaining quantity within the customer's requested delivery time. CTP helps to improve customer service, reduce inventory costs, and increase production efficiency12. References: 1 Capable to Promise (CTP) - Definition, Calculation, and Examples 3 2 CPIM Exam References - Association for Supply Chain Management
NEW QUESTION # 42
The primary outcome of frequent replenishments in a distribution requirements planning (DRP) system is that:
- A. the level of required safety stock is reduced.
- B. transportation costs decrease.
- C. more efficient load consolidation occurs.
- D. lead times to customers decrease.
Answer: A
Explanation:
The primary outcome of frequent replenishments in a distribution requirements planning (DRP) system is that the level of required safety stock is reduced. Safety stock is the extra inventory that is held to protect against demand uncertainty or supply variability. Frequent replenishments mean that the inventory is replenished more often and in smaller quantities, which reduces the risk of stockouts and the need for safety stock. Frequent replenishments also improve the inventory visibility and accuracy, which enable better demand forecasting and inventory planning. By reducing the safety stock, the company can lower its inventory carrying costs, free up working capital, and increase its inventory turnover. The other options are not correct, as they are not the primary outcome of frequent replenishments, but rather possible benefits or drawbacks of frequent replenishments, depending on the situation:
Lead times to customers decrease: This may or may not be true, depending on the distance between the distribution centers and the customers, the transportation mode and frequency, and the customer service level. Frequent replenishments may reduce the lead times if the distribution centers are closer to the customers and the transportation is fast and reliable. However, frequent replenishments may also increase the lead times if the distribution centers are far from the customers and the transportation is slow and infrequent.
Transportation costs decrease: This may or may not be true, depending on the transportation mode, distance, and volume. Frequent replenishments may reduce the transportation costs if the transportation mode is economical, the distance is short, and the volume is high. However, frequent replenishments may also increase the transportation costs if the transportation mode is expensive, the distance is long, and the volume is low.
More efficient load consolidation occurs: This is unlikely to be true, as frequent replenishments usually mean smaller shipments that are less likely to fill the capacity of the transportation vehicles. Load consolidation is the process of combining multiple shipments into one larger shipment to optimize the transportation efficiency and reduce the transportation costs. Frequent replenishments may reduce the opportunities for load consolidation and increase the transportation inefficiency and costs. References:
[CPIM Part 2 - Section A - Topic 4 - Distribution Planning]
Distribution Requirements Planning (DRP) in Supply Chain
What is DRP? (A Comprehensive Guide on Distribution Requirements Planning) Safety Stock: The Ultimate Guide Load Consolidation
NEW QUESTION # 43
A company is having trouble with raw material deliveries and has decided to develop a supplier certification program. The certification process most appropriately would start with which of the following suppliers?
- A. Suppliers with the worst performance records
- B. Suppliers with vendor-managed inventory (VMI)
- C. Suppliers recently ISO 9000 certified
- D. Suppliers of "A" classified items
Answer: D
Explanation:
A supplier certification program is a formal process of evaluating and approving potential suppliers based on certain criteria, such as quality, delivery, cost, and service. The purpose of a supplier certification program is to ensure that the suppliers meet the standards and expectations of the company and to reduce the risks and costs associated with poor supplier performance. A supplier certification program should start with the suppliers of "A" classified items, which are the most critical and valuable items for the company. These items have the highest impact on the company's profitability and customer satisfaction, and therefore require the highest level of supplier reliability and quality. By certifying the suppliers of "A" classified items, the company can improve its supply chain performance and reduce its dependence on inspection and corrective actions. This aligns with CPIM's focus on plan and manage supply and plan and manage distribution. References: The concepts are covered in detail in Module 3: Supply Management (1 and Module
7: Distribution and Logistics Management (2. You can also find more information about supplier certification programs from these sources: 3, 4, and 5.
NEW QUESTION # 44
The time spent In queue by a specific manufacturing job is determined by which of the following factors related to the order?
- A. Run time
- B. Lot size
- C. Setup time
- D. Priority
Answer: D
Explanation:
The time spent in queue by a specific manufacturing job is determined by the priority of the order. Priority is the relative importance or urgency of an order compared to other orders in the system. Priority can be assigned based on various criteria, such as due date, customer preference, profitability, or first-come-first-served.
Priority determines the order in which jobs are processed at each workstation and affects the waiting time and flow time of each job. Higher priority jobs have shorter waiting times and lower priority jobs have longer waiting times. Priority can be used as a tool to manage the trade-offs between customer service, capacity utilization, and inventory levels. References:
Managing Supply Chain Operations, Chapter 7: Scheduling and Sequencing, Section 7.2: Priority Rules CPIM Exam Content Manual, Module 6: Detailed Schedules, Section 6.2: Scheduling and Sequencing, Subsection 6.2.2: Priority Rules
NEW QUESTION # 45
One way to mitigate liability risk in the supply chain is to:
- A. use less-than-truckload (LTL) shipments more frequently.
- B. require traceability for components.
- C. push inventory to supplier locations.
- D. negotiate lower component cost.
Answer: B
Explanation:
One way to mitigate liability risk in the supply chain is to require traceability for components. Liability risk is the risk that a party may be held responsible for certain types of losses caused by its actions or products to third parties1. Traceability is the ability to track the origin, history, location, and movement of a product or a component through the supply chain2. Requiring traceability for components can help to mitigate liability risk in the supply chain by enabling the identification and verification of the quality, safety, and compliance of the components, as well as the detection and prevention of counterfeit, defective, or hazardous components.
Traceability can also facilitate the recall, repair, or replacement of faulty components, and the allocation of responsibility and accountability among the supply chain partners in case of a liability claim34. References: 1 What is a Liability Risk? - Definition from Insuranceopedia 5 2 Traceability - Wikipedia 6 3 Supply Chain Liability in the Corporate Sustainability Due Diligence ... 7 4 CPIM Exam References - Association for Supply Chain Management 8
NEW QUESTION # 46
......
CPIM-8.0 exam questions from RealValidExam dumps: https://actualtests.realvalidexam.com/CPIM-8.0-real-exam-dumps.html (152 Q&As)
